The process of formalizing acceptance of the completed project deliverables is known as:
A) product acceptance.
B) system turnover.
C) validate scope
D) control scope
Correct Answer:
Verified
Q3: When a project is completed on time,the
Q4: Helping good workers to secure good follow-on
Q5: Since projects are temporary in nature and
Q6: More organizations effectively collect lessons learned than
Q7: Celebrations of success ease the stress of
Q9: When a contract is terminated for convenience,the
Q10: Many organizations use project closeout checklists that
Q11: The Validate Scope process occurs with interim
Q12: When a project is no longer needed
Q13: A method for documenting and sharing lessons