When Considering Traditional Versus Agile Project Management, All of the Following

Question 8

Multiple Choice

When considering traditional versus agile project management, all of the following are part of the traditional project management model EXCEPT


A) Fixed scope.
B) Deliverables.
C) Continuous design.
D) Low uncertainty.
E) Conventional project teams.

Correct Answer:

verifed

Verified