The earned value of a project is the
A) Project cost to date adjusted for project scope changes.
B) Total project cost to date.
C) Cost incurred minus the planned cost.
D) Percent of the original budget that has been earned by actual work.
E) The planned time-phased baseline of the value of work scheduled.
Correct Answer:
Verified