The start of a task may be moved on a Tracking Gantt due to
A) Increase in Earned Value.
B) Lack of an update Control Chart.
C) A predecessor task starting late.
D) Increase in Earned Value and Lack of an update Control Chart.
Correct Answer:
Verified