Which of the following correctly calculates an activity's cost slope?
A) (normal cost - crash cost) / (normal time - crash time)
B) (crash cost - normal cost) / (normal time - crash time)
C) (normal time - crash time) / (crash cost - normal cost)
D) (normal time - crash time) / (normal cost - crash cost)
E) (crash cost - normal cost) / (crash time - normal time)
Correct Answer:
Verified
Q41: When it is necessary to reduce project
Q42: When reducing project duration, the duration for
Q43: When determining which activity to crash, there
Q44: Which of the following is NOT one
Q45: Which of the following is NOT a
Q47: The relationship between the normal point and
Q48: Sometimes very high _ costs are recognized
Q49: Which of the following projects would be
Q50: When a project manager must reduce project
Q51: Which of the following is NOT a
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents