When a project manager must reduce project duration but resources are constrained, creating a software program that will have fewer features than originally planned or building a house without the bonus room the owner originally specified in the plans would both be examples of
A) Fast-tracking.
B) Using critical-chain project management.
C) Reducing project scope.
D) Compromising quality.
E) Doing it twice-first fast and then correctly.
Correct Answer:
Verified
Q20: As a project is crashed and project
Q21: It is going to cost $80,000 a
Q22: All of the following are disadvantages of
Q24: Which of the following is NOT a
Q26: Compressing activities on a project with a
Q27: When the project team is salaried, which
Q30: The relationship between the normal point and
Q44: Which of the following is NOT one
Q51: Which of the following is NOT a
Q57: According to Brooks' Law, adding more people
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents