When work package estimates are made by individuals most knowledgeable about the work being performed and these estimates are then "rolled up" to find estimated costs for major deliverables and the project itself, ____________ estimating is being used.
Correct Answer:
Verified
Explanation: The bottom-up app...
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q35: Accounting would be an example of which
Q39: An external view of a Mega Project
Q41: The preferred method for situations where the
Q42: The estimating factor that considers the skill
Q43: The top-down method of estimating project time
Q45: The approach to estimating project time and
Q46: The estimating factor that considers the prevailing
Q47: The top-down method for estimating project time
Q48: The bottom-up method of estimating where work
Q49: The salary of the project manager and
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents