Annie is planning a large surprise party for her sister Gwendolyn.She has developed the following plan, including estimates of the time (in hours) and cost necessary to perform each of the tasks required.
What is Annie's total benefit from crashing this project by 6 hours?
A) $55
B) $185
C) $160
D) $240
Correct Answer:
Verified