Solved

Task X Has a Best-Case Duration of 4 Days,a Worst-Case

Question 5

Multiple Choice

Task X has a best-case duration of 4 days,a worst-case duration of 10 days,and a most likely duration of 6 days.Using this information,we can estimate a 50 percent probability that the task will be completed in no more than how many days?


A) 6.0 days
B) 3.3 days
C) 10.0 days
D) 6.3 days

Correct Answer:

verifed

Verified

Unlock this answer now