A company must make 400 units per day.The company works one 12-hour shift.What is the efficiency if the total time to complete all tasks is 23 minutes and the company is using 18 workstations?
A) 22%
B) 71%
C) 50%
D) 88%
Correct Answer:
Verified
Q35: Compared to a functional layout,cellular layouts have:
A)Less
Q39: Which process structure is most likely used
Q41: A company must make 30 units per
Q42: In line-balancing, the relationships between tasks in
Q43: Which of following is NOT a drawback
Q45: In line-balancing, takt time is the time:
A)Needed
Q46: What is the takt time in minutes,
Q47: A College of Business building that has
Q48: A company must make 30 units per
Q49: Which of the following would not be