When is it appropriate to include sunk costs in the evaluation of a project?
A) Whenever they are relatively large
B) If they improve the project's NPV
C) If they are considered to be overhead costs
D) Never
Correct Answer:
Verified
Q30: Corporate income statements are designed primarily to
Q31: In which of the following cases will
Q32: Projects that have negative NPVs should be:
A)
Q33: If the adoption of a new product
Q34: The rationale for not including sunk costs
Q36: The total depreciation tax shield equals the
Q37: A proposed project requires an initial investment
Q38: A firm invests in a 7-year project
Q39: Net working capital is expected to increase
Q40: Which one of these represents a cash