The Internal Rate of Return Is Most Reliable When Evaluating

Question 21

Multiple Choice

The internal rate of return is most reliable when evaluating:


A) a single project with alternating cash inflows and outflows over several years.
B) mutually exclusive projects of differing sizes.
C) a single project with only cash inflows following the initial cash outflow.
D) a single project with cash outflows at time 0 and the final year and inflows in all other time periods.

Correct Answer: