End item A requires three component parts: B,C,and D.The bill of materials indicates that for each completed A,one unit of B,2 units of C,and 1 unit of D are required.Current inventory for the four items is as follows: there are 18 As,40 Bs,50 Cs and 35 Ds in stock.If the lead time for all items is one week and there are no scheduled receipts for any item,how many units of product A can be delivered to customers at the start of next week (week 2) ?
A) 13
B) 25
C) 31
D) 43
Correct Answer:
Verified
Q5: Successful MRP system implementation includes
A) implementation planning.
B)
Q6: Cycle counting
A) is counting a fraction of
Q7: The parts explosion results in the following
Q8: The gross requirements of a part in
Q9: Bills of materials are kept current with
Q11: The master production schedule for Product A
Q12: The bill of materials
A) shows how much
Q13: A requirements-based system derives orders from
A) customer
Q14: Safety stock in an MRP system
A)
Q15: Which system specifies the output of the
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents