Which of the following is correct regarding future demand for component parts?
A) Future demand in an order-point system is based on the master production schedule.
B) Future demand in an MRP system is based on the past history of demand for each component part.
C) Future demand in an MRP system is based on the master production schedule.
D) None of the above.
Correct Answer:
Verified
Q34: Which of the following would NOT likely
Q35: Which of the following is NOT a
Q36: The purpose of the shop floor control
Q37: A manufacturing execution system (MES)
A) is another
Q38: Which of the following is NOT an
Q39: When MRP is extended all the way
Q41: The master schedule should be frozen inside
Q42: MRP is a type of pull system.
Q43: Compare and contrast MRP systems and order-point
Q44: The master schedule is prepared for product
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents