If mean daily demand is 20 units,lead time is 7 days,the standard deviation of demand during lead time is 12.0 units,and management has a preferred service level of 99.9% (z = 3) ,the reorder (R) level for the item would be
A) 176.00 units.
B) 56.00 units.
C) 152.00 units.
D) 104.00 units.
Correct Answer:
Verified
Q35: At the economic order quantity,
A) the annual
Q36: Which of the following statements about service
Q37: Determinants of reorder levels (order point quantities)include
Q38: Which of the following is correct?
A) Anticipation
Q39: If the actual order quantity Q is
Q41: Lincoln Machine Tool Company maintains an inventory
Q42: The EOQ formula could be modified to
Q43: A large hospital that batches orders for
Q44: Inventory turnover for a given period can
Q45: Given that unit item cost = $30,annual
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents