Solved

Which of the Following Statements About Batch Scheduling Is INCORRECT

Question 26

Multiple Choice

Which of the following statements about batch scheduling is INCORRECT?


A) Dispatching is used to determine the job priority at a work center.
B) The priority of a job, once determined, does not change as it progresses through the production process.
C) Finite scheduling in batch systems recognizes the limited processing capacity of the facility and does not allocate more capacity than is available.
D) The theory of constraints argues that scheduling can be improved by increasing capacity at bottleneck operations.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents