It takes 1 minute to remove a burger from the cooler.The burger is cooked for 2 minutes and requires constant monitoring (the worker cannot do something else during cooking).Cooked burgers are assembled into sandwiches with buns,lettuce,and tomato slices.This step takes 45 seconds per sandwich.Finally,packaging the sandwich takes about 10 seconds.What is the bottleneck in the process?
Why?
Correct Answer:
Verified
The bottleneck is the cooking operation...
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q34: Flow rate is
A) the same as process
Q35: Process redesign tends to be cross-functional in
Q36: If there are multiple resources that process
Q37: Consider the following two statements concerning business
Q38: Flowcharting requires Microsoft Visio or similar flowcharting
Q39: Which of the following statements is/are correct?
(1)It
Q40: Throughput time is
A) the same as the
Q41: A store open 24 hours per day
Q43: Changing the information gathered and used for
Q44: Provide two examples for each of the
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents