Which of the following statements is incorrect with respect to revenue recognition of construction contracts?
A) The percentage-of-completion method is to be applied for fixed price contracts if the recognition criteria are satisfied.
B) IASB (2011) Revenue from Contracts with Customers requires individual construction contracts to be accounted for separately and the requirements of the standard to be applied separately to each contract.
C) The percentage-of-completion method should be used, provided certain conditions are met that enable the outcome of the contract to be reliably measured.
D) Percentage-of-completion method requires contract revenue to be matched with progress billings, resulting in the reporting of revenue, expenses and profit which can be attributed to the amount billed to customers.
Correct Answer:
Verified
Q47: In accordance with IASB (2011)Revenue from Contracts
Q49: Lonsdale Plc sells mobile phones and provides
Q49: A group of contracts shall be treated
Q50: Werribee Direct Plc is a mail order
Q54: Bellarine Plc is publisher of Mode magazine
Q65: Describe the output and input measures of
Q66: When a performance obligation is satisfied,an entity
Q70: IASB and FASB initiated a joint project
Q73: Discuss how the use of call and
Q78: Which of the following statements is not
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents