The Option to Wait

Question 50

Multiple Choice

The option to wait:
I.may be of minimal value if a project is dependent upon rapidly changing technology.
II.is partially dependent upon the discount rate applied to the project being evaluated.
III.is defined as temporarily shutting down a project for a period of time.
IV.has a value equal to the NPV of a project if it is started at a later date minus the NPV if the project is started today.


A) I and III only
B) II and IV only
C) I and II only
D) II, III, and IV only
E) I, II, and IV only