When using the adjusted present value (APV) to evaluate a capital budgeting problem,the appropriate discount rate for foreign loans is:
A) the cost of equity for a leveraged firm.
B) the cost of equity for an unleveraged firm.
C) the firm's domestic cost of debt.
D) the firm's foreign cost of debt.
Correct Answer:
Verified