In a work center, machine A has a 10-minute set-up time per batch and a 2-minute per unit run time.Machine B performs the identical function but has a set-up time of 30 minutes and a 1-minute run time per unit.The work center makes products in batches ranging from 1 unit to 100 units.Assuming capacity is not a limitation on either machine, in order to minimize the total processing time, on which batches should machine B be used?
A) All batches should be run on machine B.
B) Batches of more than 20 units should be run on machine B.
C) Batches of fewer than 80 units should be run on machine B.
D) Batches with up to 50 units should be run on machine B.
E) No batches should be run on machine B.
Correct Answer:
Verified
Q6: The closer the customer is to the
Q9: The term "assembly line" refers to progressive
Q15: A make-to-order firm will work with the
Q24: The placement of which of the following
Q26: Which of the following is not considered
Q26: You are hired as a consultant to
Q27: An example of an assemble-to-order firm is
Q33: Which of the following is not a
Q36: Assume a fixed cost for a process
Q38: Which of the following basic types of
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents