Texas Metal Company
Texas Metal Company has developed standard overhead costs based on a monthly capacity of 180,000 machine hours as follows:
During November,90,000 units were scheduled for production,but only 80,000 units were actually produced.The following data relate to November:
Actual machine hours used were 165,000.
Actual overhead incurred totaled $1,378,000 ($518,000 variable plus $860,000 fixed) .
All inventories are carried at standard cost.
Refer to Texas Metal Company.The fixed overhead spending variance for November was
A) $40,000 U.
B) $40,000 F
C) $60,000 F
D) $60,000 U.
Correct Answer:
Verified
Q194: The sum of the material mix and
Q195: Define the following terms: standard cost system,total
Q196: List and discuss briefly the three standards
Q197: Industrial Solutions Company
Industrial Solutions Company manufactures a
Q198: The following information is available from
Q200: Industrial Solutions Company
Industrial Solutions Company manufactures a
Q201: Why are fixed overhead variances considered noncontrollable?
Q202: Aldrich Company
Aldrich Company has the following
Q203: Explain the source of variable overhead spending
Q204: Roberts Company
Roberts Company has the following
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents