Given the Following Data for Project M Calculate the NPV

Question 37

Multiple Choice

Given the following data for Project M calculate the NPV of the project.  Cash flow in real terms: C0C1C2 Real discount rate =5%200150120 Nominal discount rate =10%\begin{array} { l l l c } \text { Cash flow in real terms: } & \mathrm { C } _ { 0 } & \mathrm { C } _ { 1 } & \mathrm { C } _ { 2 } \\\text { Real discount rate } = 5 \% & - 200 & 150 & 120 \\\text { Nominal discount rate } = 10 \% & & &\end{array}


A) $51.70
B) $35.54
C) $45.21
D) $70.00

Correct Answer: