Which of the following are limitations of PERT?
(I) Time estimates may include a fudge factor.
(II) Important activities may be overlooked.
(III) It is an after-the-fact analysis.
A) I and II
B) I, II, and III
C) I and III
D) II and III
E) I only
Correct Answer:
Verified
Q50: Once a project is underway, the project
Q53: Activity 7-8 is directly preceded by two
Q57: Which of the following would probably not
Q58: A popular tool for planning and scheduling
Q62: The project management strategy of injecting additional
Q68: There are four activities on the critical
Q69: Gantt charts are most closely associated with
A)JIT.
B)PERT.
C)MRP.
D)MRPII.
E)Six
Q70: In project network analysis, "slack" refers to
Q72: There are four activities on the critical
Q79: Activity C has an early start time
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents