A project has the activities and activity times (days) listed below. Determine the probability that the project will require more than 15 days from start to finish.  Activity  Exp.Time  St.Dev 1261.312462.701371.003460.00\begin{array} { l l l } \text { Activity } & \text { Exp.Time } & \text { St.Dev } \\\hline 1 - 2 & 6 & 1.31 \\2 - 4 & 6 & 2.70 \\1 - 3 & 7 & 1.00 \\3 - 4 & 6 & 0.00\end{array}

Correct Answer:

verifed

Verified

The probability of t...