Based on the cost information given in the following table, which set of job-machine pairs reflects the minimum-cost solution using the Assignment method?
A) 1-B, 2-A, 3-C
B) 1-A, 2-B, 3-C
C) 1-C, 2-A, 3-B
D) 1-B, 2-C, 3-A
E) 1-C, 2-B, 3-A