Eva, the owner of Eva's Second Time Around Wedding Dresses, currently has five dresses to be altered, shown in the order in which they arrived: If Eva uses the earliest due date first (EDD) priority rule to schedule these jobs, what will be the average job tardiness?
A) 2 hours
B) 2.2 hours
C) 2.33 hours
D) 2.4 hours
E) 3 hours