Solved

A Company Is Designing a Product Layout for a New

Question 98

Multiple Choice

A company is designing a product layout for a new product. It plans to use this production line eight hours a day in order to meet projected demand of 480 units per day. The tasks necessary to produce this product are:  Task  Time (secs)   Immediate Predecessor u30 none v30uw6ux12wy54xz30v,y\begin{array} { l l l } \text { Task } & \text { Time (secs) } & \text { Immediate Predecessor } \\\hline \mathrm { u } & 30 & \text { none } \\\mathrm { v } & 30 & \mathrm { u } \\\mathrm { w } & 6 & \mathrm { u } \\\mathrm { x } & 12 & \mathrm { w } \\\mathrm { y } & 54 & \mathrm { x } \\\mathrm { z } & 30 & \mathrm { v } , \mathrm { y }\end{array} Without regard to demand, what is the minimum possible cycle time (in seconds) for this situation?


A) 162
B) 72
C) 54
D) 12
E) 60

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents