Solved

In a Manufacturing Facility Producing Fasteners,a Foreman Suspects That the Diameter

Question 72

Multiple Choice

In a manufacturing facility producing fasteners,a foreman suspects that the diameter of the bolts produced by his first-shift workers is greater than the diameter of the bolts produced by his second-shift workers.He takes a sample of 5 bolts from the first shift and a sample of 4 bolts from the second shift and measures the diameters in inches.Below are the results from 5 first shift and 4 second-shift observations.The bolt diameter measurements are not normally distributed.  Bolt Diameter (inches)   1st shift  2nd shift 2.011.802.251.951.982.302.052.002.03\begin{array} { c c } & { \text { Bolt Diameter (inches) } } \\\text { 1st shift } & \text { 2nd shift } \\2.01 & 1.80 \\2.25 & 1.95 \\1.98 & 2.30 \\2.05 & 2.00 \\2.03 &\end{array}
At ? = .05,can we conclude that his suspicion is correct?


A) Reject the null hypothesis,the diameter is greater for 1st shift versus 2nd shift.
B) Do not reject the null hypothesis,there is no evidence that the diameters differ by shift.
 Bolt Diameter (inches)   1st shift  2nd shift 2.011.802.251.951.982.302.052.002.03\begin{array} { c c } { \text { Bolt Diameter (inches) } } \\\text { 1st shift } & \text { 2nd shift } \\2.01 & 1.80 \\2.25 & 1.95 \\1.98 & 2.30 \\2.05 & 2.00 \\2.03 &\end{array}

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents