A job was budgeted to require 3 hours of labor per unit at $8.00 per hour. The job consisted of 8,000 units and was completed in 22,000 hours at a total labor cost of $198,000. What is the direct labor rate variance?
A) $22,000 unfavorable.
B) $22,000 favorable.
C) $16,000 unfavorable.
D) $16,000 favorable.
E) $6,000 unfavorable.
Correct Answer:
Verified
Q48: Which department is often responsible for the
Q64: Based on a predicted level of production
Q65: Based on a predicted level of production
Q77: A job was budgeted to require 3
Q81: Use the following data to find the
Q83: Hassock Corp.produces woven wall hangings.It takes 2
Q84: Use the following data to find the
Q85: Use the following data to find the
Q86: A job was budgeted to require 3
Q93: Summerlin Company budgeted 4,000 pounds of material
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents