Beluga Corp. has developed standard costs based on a predicted operating level of 352,000 units of production, which is 80% of capacity. Variable overhead is $281,600 at this level of activity, or $0.80 per unit. Fixed overhead is $440,000. The standard costs per unit are:
Beluga actually produced 330,000 units at 75% of capacity and actual costs for the period were:
Calculate the following variances and indicate whether each variance is favorable or unfavorable:
(1) Direct labor efficiency variance: $________
(2) Direct materials price variance: $________
(3) Controllable overhead variance: $________
Correct Answer:
Verified
Q155: Hatter,Inc.allocates fixed overhead at a rate of
Q158: Linx Company's output for a period was
Q184: If Mercury Company's actual overhead incurred during
Q186: Tiger, Inc. budgeted the following overhead
Q187: The following information comes from the flexible
Q188: Selected information from Richards Company's flexible budget
Q194: In producing 700 units of product last
Q194: The following information comes from the records
Q196: During November, Gliem Company allocated overhead to
Q200: Ransom, Inc. budgets direct materials cost at
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents