At the end of June, the job cost sheets for Kennedy Manufacturing show the following total costs accumulated on three custom jobs.
Job 203 was started in production in May and the following costs were assigned to it in May: direct materials, $12,000; direct labor, $6,000; and overhead $8,700. Jobs 204 and 205 are started in June. Overhead cost is applied with a predetermined rate based on direct labor cost. Jobs 203 and 204 are finished in June, and Job 205 will be finished in July. No raw materials are used indirectly in June. Using this information, answer the following questions assuming the company's predetermined overhead rate did not change.
a. What is the cost of the raw materials requisitioned in June for each of the three jobs?
b. How much direct labor cost is incurred during June for each of the three jobs?
c. What predetermined overhead rate is used during June?
d. How much total cost is transferred to finished goods during June?
Correct Answer:
Verified
Q184: A company charged the following amounts of
Q190: A company's ending inventory of finished goods
Q194: Prepare journal entries to record the following
Q196: A company's job order costing system applies
Q198: Lock Production Co. applies factory overhead to
Q201: When factory payroll for indirect labor is
Q204: Drop Anchor takes special orders to manufacture
Q205: The predetermined overhead rate for Shilling
Q206: Booth Manufacturing uses a job order
Q210: _, or customized production, produces products in
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents