A Government Is Considering Undertaking a Construction Project of an Increasing

Question 158

Multiple Choice

A government is considering undertaking a construction project of an increasing scale (ranging from 1, 2, 3, to 4) . The estimated marginal costs and marginal benefits of each successive scale of the project are given in the table below. A government is considering undertaking a construction project of an increasing scale (ranging from 1, 2, 3, to 4) . The estimated marginal costs and marginal benefits of each successive scale of the project are given in the table below.   What is the total cost and total benefit of the scale-3 project? A)  Total cost is $18 million, and total benefit is $19 million. B)  Total cost is $24 million, and total benefit is $27 million. C)  Total cost is $37 million, and total benefit is $41 million. D)  Total cost is $65 million, and total benefit is $66 million. What is the total cost and total benefit of the scale-3 project?


A) Total cost is $18 million, and total benefit is $19 million.
B) Total cost is $24 million, and total benefit is $27 million.
C) Total cost is $37 million, and total benefit is $41 million.
D) Total cost is $65 million, and total benefit is $66 million.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents