The Gears Department of Cycle Company Has Budgeted Monthly Manufacturing

Question 32

Multiple Choice

The gears department of Cycle Company has budgeted monthly manufacturing overhead cost of $40,000 plus $5 per direct labour hour. The flexible budget report reflects $120,000 for total budgeted manufacturing cost for the month. What is the actual level of activity achieved during the month?


A) 16,000 direct labour hours.
B) 22,400 direct labour hours.
C) 24,000 direct labour hours.
D) 32,000 direct labour hours.