A machine shop has two machines,A and
B.Four jobs need to be processed through machine A first and B second.Job 1 will take one hour on machine A and three hours on machine
B.Job 2 will take three hours on A and two hours on
B.Job 3,seven on A and three on
B.Job 4,five hours on A and one hour on
B.Using Johnson's rule,in what order should these jobs be done?
Correct Answer:
Verified
Q46: Which priority rule is so powerful that
Q50: Assume there are five jobs (i.e., A,
Q81: A job has 10 days of processing
Q82: Which of the following is a priority
Q96: A job has 5 days of processing
Q103: The assignment method is useful in solving
Q105: Which of the following is a principle
Q107: Which of the following is not one
Q112: Which of the following is a tool
Q119: Which of the following is one of
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents