A time study was made of a job to develop new time standards.A worker was observed for 30 minutes.During that time,40 units were produced.The analyst rated the worker as performing at a 120 percent performance rate.Allowances for rest and personal time are 20 percent.What is the standard time for this task?
A) 0.75 minutes
B) 0.98 minutes
C) 1.00 minutes
D) 1.08 minutes
E) 1.33 minutes
Correct Answer:
Verified
Q49: Which of the following is not a
Q50: What are the four reasons that time
Q51: Describe the distinction between horizontal and vertical
Q52: A time study was made of a
Q53: A worker was producing a product for
Q55: If the normal time for a job
Q56: If the normal time for a job
Q57: Which of the following are not used
Q58: In work sampling,which one of the following
Q59: Which of the following is not a
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents