Solved

If a Person Performing a Task Has Been Achieving an 85

Question 54

Short Answer

If a person performing a task has been achieving an 85 percent learning curve and if it took 1 minute to produce the first unit, what will be the total time to produce 1,000 units? ______________________

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents