Faced with the task of planning the company convention and trade show,Marcia planned out all the deadlines and activities by starting with the actual convention and trade show and worked her way in reverse to today's date.From this,Marcia was able to lay out an exact schedule for completing all her tasks.Marcia was using the tactic of:
A) stakeholding.
B) tracing.
C) backscheduling.
D) projecting.
Correct Answer:
Verified
Q18: Which of the following holds true of
Q19: The critical path in a PERT chart
Q20: Tracey has noticed that the team is
Q21: Which of the following as a problem-solving
Q22: Parry is a project manager.By skipping which
Q24: By adding the actual schedules on a
Q25: In determining project participants and stakeholders,the team
Q26: Managers often need to use _ techniques,which
Q27: Using which of the following actions can
Q28: Establishing checkpoints and control mechanisms can help
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents