Question 23

Multiple Choice

Which of the following statements about critical path scheduling is not true?


A) The critical path is the longest path through the network
B) Critical path scheduling allows managers to not manage non-critical activities
C) As a manager we need to know the critical path to identify which activities we should focus our efforts on controlling
D) A delay in a critical path activity delays the expected project completion time
E) Critical path analysis lets us know which activities do not need to be managed as strictly

Correct Answer: