Which of the following statements about critical path scheduling is not true?
A) The critical path is the longest path through the network
B) Critical path scheduling allows managers to not manage non-critical activities
C) As a manager we need to know the critical path to identify which activities we should focus our efforts on controlling
D) A delay in a critical path activity delays the expected project completion time
E) Critical path analysis lets us know which activities do not need to be managed as strictly
Correct Answer:
Verified
Q15: What usually does not need to be
Q16: Supply Management calls for contract and relationship
Q17: Some of the common approaches that buying
Q18: A typical cost ratio expresses the cost
Q19: As a project manager,we need to know
Q20: Critical path analysis lets us know the
Q21: Assume that for one supplier: quality cost
Q22: Which of the following is not a
Q24: Which of the following is not a
Q25: In managing the relationship between buyers and
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents