Which of the following is not a criterion in favor of using cost-type arrangements?
A) Research and development increases technical risk
B) Project completion is in doubt
C) Product specifications are incomplete
D) Delivery times are certain
E) High-dollar, highly uncertain procurements are involved
Correct Answer: