The information calculated from the forward and backward pass can be used for:
A) Identifying the critical path
B) Calculating slack
C) Determining the final completion date of the project
D) All of the above
Correct Answer:
Verified
Q4: Which of the following statements is true
Q15: Which of the following statements is NOT
Q16: The critical path of the following network
Q17: Gantt charts are effective for project scheduling
Q19: Project managers' work includes:
A)Planning,Scheduling,Control,and Closing
B)Planning,Scheduling,Starting,and Ending
C)Scheduling,Control,Starting,and Ending
D)None
Q21: Which of the following statements about critical
Q25: PERT assumes that the statistical variation in
Q28: The early start and late start times
Q32: A forward pass is required while computing
Q36: A work breakdown structure is used in
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents