By using the PERT weighted average for each activity duration estimate,the total project duration estimate does not account for the risk or uncertainty in the individual activity estimates.
Correct Answer:
Verified
Q11: A Tracking Gantt chart is based on
Q29: Project management software does not have the
Q30: _ involves analyzing activity sequences,activity resource estimates,and
Q32: Fast tracking can end up lengthening the
Q33: _ involves controlling and managing changes to
Q35: _ involves identifying and documenting the relationships
Q36: The main outputs of the _ process
Q37: _ involves estimating the number of work
Q38: The critical path always includes the most
Q39: Most projects have one path through a