The ____ Provide(s)schedule-Related Information About Each Activity,such as Predecessors,successors,logical Relationships,leads
The ____ provide(s) schedule-related information about each activity,such as predecessors,successors,logical relationships,leads and lags,resource requirements,constraints,imposed dates,and assumptions related to the activity.
A) activity list
B) milestones
C) activity descriptions
D) activity attributes
Correct Answer:
Verified
Q11: A Tracking Gantt chart is based on
Q23: In a Gantt chart created in Microsoft
Q24: One of PERT's main disadvantages is that
Q25: Outputs from _ include work performance measurements,organizational
Q26: _ involves identifying the specific activities that
Q27: A fast and easy way to determine
Q29: Project management software does not have the
Q30: _ involves analyzing activity sequences,activity resource estimates,and
Q32: Fast tracking can end up lengthening the
Q33: _ involves controlling and managing changes to
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents