____ Use(s)probabilistic Time Estimates-Duration Estimates Based on Using Optimistic,most Likely,and
____ use(s) probabilistic time estimates-duration estimates based on using optimistic,most likely,and pessimistic estimates of activity durations-instead of one specific or discrete duration estimate.
A) Critical Path Analysis
B) Gantt charts
C) Critical Chain Scheduling
D) PERT
Correct Answer:
Verified
Q56: The critical path is the _ path
Q57: _ is the amount of time an
Q58: _ dependencies are sometimes referred to as
Q59: _ dependencies involve relationships between project and
Q60: The activity list,activity attributes,activity resource requirements,resource calendars,project
Q62: _ involves the processes required to ensure
Q64: _ states that work expands to fill
Q65: _ involves doing activities in parallel that
Q66: _ is a technique for making cost
Q71: In a(n) _ relationship, the "from" activity
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents