In the ____,you use a similar project's WBS as a starting point.
A) top-down approach
B) bottom-up approach
C) mind-mapping approach
D) analogy approach
Correct Answer:
Verified
Q23: The _ should list and describe all
Q46: _ is a process for identifying and
Q48: Key inputs for preparing the project scope
Q51: A(n)_ project scope statement is an important
Q54: _ uses highly organized and intensive workshops
Q55: The _ approach involves refining the work
Q56: The main outputs of _are the project
Q56: A(n)_ is a task at the lowest
Q57: The goal of _ is to influence
Q65: PMI uses the term "_" to describe