Negative and positive risks should always be included in the same probability/impact matrix or chart.
Correct Answer:
Verified
Q6: Risk events refer to specific, certain events
Q7: The last step in project risk management
Q7: Few organizations develop their own risk questionnaires.
Q9: It is uncommon for people to identify
Q10: A potential response to the risk event
Q11: The cost for risk management should not
Q13: You can break down the technology risk
Q15: A probability/impact matrix or chart lists the
Q16: Before you can improve project risk management,you
Q20: The Delphi technique is a systematic, interactive