_____ involves shifting the consequence of a risk and responsibility for its management to a third party.
A) Risk avoidance
B) Risk acceptance
C) Risk transference
D) Risk mitigation
Correct Answer:
Verified
Q42: The term _ is used to describe
Q42: _ involves allocating ownership of the risk
Q43: A project _ is an uncertainty that
Q46: _ is the process of understanding what
Q48: _ involves changing the size of the
Q50: _ involves doing whatever you can to
Q51: _ involves reducing the impact of a
Q52: The main output of the _ process
Q59: A(n) _ is a hierarchy of potential
Q60: A(n) _ documents the procedures for managing