A simple project listing of five activities,their predecessors and their respective time estimates are presented below:
Using CPM,what is the Latest Finish Time for the last activity in this project (i.e. ,the total time to complete the project) ?
A) 10 days
B) 7 days
C) 8 days
D) 12 days
E) 9 days
Correct Answer:
Verified