A company must perform a maintenance project consisting of seven activities.The activities,their predecessors,and their respective time estimates are presented below:
Using CPM,what is the Latest Finish Time for the last activity in this project (i.e. ,the total time to complete the project) ?
A) 9 days
B) 10 days
C) 11 days
D) 12 days
E) 13 days
Correct Answer:
Verified
Q41: Which of the following is a graphic
Q43: You have just been assigned to oversee
Q45: An advantage of a pure project where
Q46: In a Gantt chart, the horizontal axis
Q49: Some of the advantages of a functional
Q50: What is a work breakdown structure?
A)A list
Q51: A company must perform a maintenance
Q56: PERT is an abbreviation for which of
Q58: For an activity in a CPM analysis,the
Q59: For an activity in a CPM analysis
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents