For an activity in a CPM analysis the Early Finish time is 20 and the Late Finish time is 20.Which of the following statements is true?
A) The activity's late start must happen before its early start
B) The activity is on the critical path
C) The slack for this activity is 20
D) The duration of this task is zero
E) The duration of this task is 20
Correct Answer:
Verified
Q43: You have just been assigned to oversee
Q45: An advantage of a pure project where
Q52: Some of the advantages of a functional
Q54: For an activity in a CPM analysis,the
Q56: simple project listing of five activities and
Q57: simple project listing of five activities,their predecessors,and
Q63: In CPM analysis, it is generally expected
Q64: You know when you have arrived at
Q64: In a project analysis using three time
Q67: You have just performed a CPM analysis
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents